150 MW GRID CONNECTED WIND POWER PROJECT – SECI III

Dayapar, Taluka: Kutchh, Gujarat – India

  • Client:

    Adani Green Energy Ltd

  • Project:

    EPC for 33 KV Unitised Substation (USS) on Elevated platform for 2.2 MW windmill of Suzlon
    72 Nos (150 MW) windmills executed

OUR SCOPE

  • 33 KV Evacuation on H pole from Wind Turbine to Transmission line
  • Erection, Testing and Commissioning 33KV USS which includes Isolator, Insulator, LA, Line Conductor, Transformer, HT Panel, Bus Duct, LT panel and Control Panel work.
  • HT, LT & Control Cables including Trenching, Cable Tray and Cable Termination
  • Earthing Grid, Treated Earth pit work, Street-Light Pole work
  • CEIG / CEA Approval process and all documentation