20 MW Grid Connected Solar Power Project
Kanasar near Jodhpur, Rajasthan
-
Client:
Adani Green Energy
-
Consultant:
Adani Solar Group
OUR SCOPE
- Erection, Testing and Commissioning of Electro – Mechanical System
- Installation and Commissioning of String Inverters and AC Boxes
- Installation and Commissioning of Solar Modules, MC4 connectors, AC & DC cable
- 5 MW Substations which includes Inverter Duty Transformer (IDT) HT panel, LT panel and Busduct
- Earthing Grid, Treated Earth pit, Early Streamer Lightning Poles, Earthing of Solar Modules and 5 MW Substations
- HT and LT Cables including Trenching, Cable Tray and Cable Termination
- 33 KV Evacuation on H pole, ABT Meter, 33 KV CT, 33 KV PT
- CEIG approval of Entire Power Plant