Substation Replacement Project

Paraburdoo, Tom Price and Channar Iron Ore Deposits – Western Australia

  • Project:

    Rio Tinto, Australia

  • Client:

    BEC Engineering – Perth, Australia

OUR SCOPE

  • Detailed Engineering Design
  • Single Line Drawings
  • Control Schematics
  • Termination Diagrams
  • Interconnection Diagrams
  • Substation Layouts

IceCube completed Engineering design for detailed engineering for 40 Substations replacement project of Rio Tinto. This was done in record time of 4 months. The design was done to minimize downtime when substation was replaced.